What is a bill of materials (BOM)?
A bill of materials (BOM) is the recipe for one finished item: the list of every material and part, with the quantity of each, needed to make one unit or one batch. A carpenter's BOM for a study table lists the board, legs, screws and polish; multiplied by the number of tables, it tells you what to buy, what to issue and what each one costs.
A BOM for one study table, with its cost
Quantities are per finished table. The board line carries an 8% wastage allowance for offcuts, added on top of the 1.2 sq m the table actually uses.
| Quantity per table | Cost | |
|---|---|---|
| Plywood board, 18 mm | 1.2 sq m + 8% = 1.296 sq m | ₹1,555 at ₹1,200 per sq m |
| Wooden legs | 4 pieces | ₹800 at ₹200 each |
| Screws | 16 pieces | ₹48 at ₹3 each |
| Polish | 0.25 litre | ₹100 at ₹400 a litre |
| Cutting, fixing and polishing | 3 hours | ₹450 at ₹150 an hour |
| Cost of one table | All lines | ₹2,953 |
Kinds of BOM you will meet
The idea is the same in a furniture workshop, a sweet shop kitchen and a small engineering unit. What changes is how many levels the recipe has.
Single-level BOM
One finished item and its direct materials. Enough for most small workshops.
Multi-level BOM
A component is itself made from a BOM. A steel gate needs a frame, and the frame has its own BOM of pipes, sheet and welding rods.
Recipe or batch BOM
Quantities for a batch rather than one piece, with a process loss. A sweet shop's 10 kg of barfi lists khoa, sugar and ghee by the kilo.
Kit BOM
A trader's hamper or combo pack: no making, just several stock items sold as one. Selling the kit reduces each item's stock.
What a BOM is used for
Once the BOM is right, the arithmetic for buying, issuing and costing follows from it. Take an order of 50 tables.
- Work out what to buy
- Explode the BOM for the order: 50 tables need 200 legs. With 60 in stock, buy 140.
- Issue to the work floor
- Issue exactly what the BOM says for the quantity being made, so any extra used shows up as a variance.
- Cost the product
- Material plus operations gives the cost of one unit, ₹2,953 here, and so the lowest price that still makes money.
- Send work outside
- A BOM line tells a job worker what material goes out with the job and what should come back.
- Account for scrap
- Offcuts and scrap that can be sold are credited back against the cost of the finished item.
How Dhaaga handles BOMs
The BOM module is shared by every trade that makes or assembles something, from a mithai kitchen to a fabrication shop.
Wastage on each line
Each material line can carry a wastage allowance, added on top of the net quantity, and a BOM can carry a process loss.
Multi-level
A sub-assembly with its own BOM is exploded down to its raw materials for issue and for purchase requirements.
Cost roll-up
Material lines at current rates plus operation costs roll up into the cost of one unit, through every level.
Scrap credit
Sellable scrap and by-products on a BOM are credited against the cost of the finished item.
Questions people ask first.
Bill of materials. In food and chemical businesses the same thing is often called a recipe or formula.
Multiplying the BOM by the quantity to be made, through every level, to get the total of each raw material needed. For 50 tables at 4 legs each, the explosion says 200 legs.
A BOM says what goes into the product. A routing says which operations are done, in what order, on which machine or by which team.
Only for kits and combos it sells as one item, such as a gift hamper or a tool set. A shop that only buys and sells finished goods does not.
Extra material added to cover offcuts and loss. A line that needs 1.2 sq m with an 8% allowance asks for 1.296 sq m.
Whoever knows how the product is made: the owner or master craftsman in a small unit, the production or design team in a larger one. Accounts should check it against actual issues every few months.
Put one real day through it.
Not a sandbox with sample data — your own bills, your own items, your own customers. By evening you will know whether this runs your business.